Saturday, January 19, 2008

Hmmm.....

The framing hasn't started as yet... not sure why???
Visited yesterday and today but no work...








We do have some cracks in the slab in various places but will keep our eye on them to see if they increase in size and go from there....

The builders timeframe was:

The time frame provided by our builder was:


14/12/07 - Site cut - COMPLETED 11/12/07

7/01/08 - Set Out - COMPLETED 11/12/07

8/01/08 - Drains - COMPLETED 7/1/08

9/01/08 - Underground Power - COMPLETED 9/1/08

10/01/08 - Concreter to start - COMPLETED 15/1/08

18/01/08 - Frame to commence - ???? nothing yet??? hmmm wait and see???


Hopefully next week we should see the skeleton for our new house???


No comments: