Have been advised that "D" is eager to get as much done prior to Christmas as he can... (i think i like him already). We are supposed to be getting the meter/power installed by Monday 24/12...
Do they still work right up to Christmas eve????
But not sure if the timeline is still in the correct order now....
14/12/07 - Site cut - DONE
7/01/08 - Set Out - DONE
8/01/08 - Drains
9/01/08 - Underground Power - BEFORE X'MAS???
10/01/08 - Concreter to start
15/01/08 - Commence Framing
Can the meter/power be installed before the drains???
Does that mean that security fencing needs to go up????
Will check out the block tomorrow.... and maybe on Monday arvo to see if anything has changed.
Definitely more updates to come....
Well done "D"..... you are off to a great start already....
Friday, December 21, 2007
Maybe more news???
at 11:09 PM